Pearlington Church Constuction
The construction of the church building in Pearlington, Mississippi has begun. The tentative (subject to passed inspections) dates and tasks are:
April 18 - 29 Stacking logs for outside walls
May 1 - 6 Setting trusses, interior walls
May 7 - 13 Decking, roofing
May 14 - 20 Electrical, plumbing, rough-in
May 21-27 Drywall
Cooks are also appreciated. Any week you are available to help in this work, please inform Steve Baker, Mike Northcutt, or Darrell Gibson.
<< Home